今天昆明裝修公司將要為您帶來的是昆明老別墅改造的知識,別墅水電改造是指根據家庭人口、生活習慣、審美觀念對原有開放商使用的水電路進行合理的規劃與劃分。別墅水電改造又分為水路改造和電路改造,水電改造一直是家庭裝修中非常重要的環節,其裝修質量的優劣與屋主息息相關。因此,業主在水電改造施工中需要十分留意,最好在現場監工,可避免某些不和規范的施工現象發生。

Today, Kunming Decoration Company will bring you the knowledge of the transformation of old villas in Kunming. The villa hydropower transformation refers to the rational planning and division of the water circuits used by the original openers according to the family population, living habits and aesthetic concepts. The hydropower transformation of the villa is divided into waterway reconstruction and circuit transformation. Hydropower transformation has always been a very important part of the home decoration. The quality of the decoration is closely related to the owner. Therefore, the owner needs to pay great attention to the construction of hydropower, it is best to supervise the site, to avoid some construction problems that are not normal.

中航城

一、別墅水電改造前應該準備的事情


1、收房完成后,裝修手續已經辦理完畢了;


2、室內主體墻拆改項目已經完成了;


3、家具、電器等的擺放位置和規格,都應該確定了;


4、頂面吊頂燈位置確定好了;


5、水電平面布置圖以及造型燈位置布置好了;


6、廚房內確定好插座位置、抽油煙機、燈位、水管位置和走向都布置好了;


7、提前預約好水電工程師上門規劃準備定位點,并現場做出工程量預算;

1. After the completion of the house, the decoration procedures have been completed;


2. The indoor main wall demolition project has been completed;


3. The placement and specifications of furniture and electrical appliances should be determined;


4. The position of the top ceiling light is determined;


5. The layout of the hydropower plane and the position of the modeling lamp are arranged;


6, in the kitchen to determine the location of the socket, range hood, lamp position, water pipe position and direction are arranged;


7. Make an appointment in advance for the hydropower engineer to plan and locate the site, and make the project budget on site;

中航城

二、別墅水電改造施工流程


1、水電定位


水電改造施工的第一步就是水電定位,也就是根據業主的要求定位出全屋開關插座的位置和水路接口的位置,水電工需要根究開關、插座、水龍頭的位置按照圖紙上的走向給用戶將清楚。而且要注意“水走天、電走地”的原則,即水管走天棚,強弱電盡量走地面,而且強、弱電之間不能交叉,而且平行距離需大于30厘米。


配電箱的位置需要設計時需要考慮到使用的便利性、隱蔽及安全性。還要注意和外來主線直接連接,電氣線路不可隱蔽在承重墻內、柱內。


電路中的插座、開關和燈具線路在設計時要考慮到室內空間的可變性,為不同空間的使用狀況做準備,減少部分使用者在使用過程中的再規劃設計的障礙,比如書桌、裝飾柜、電器設備的移動對電路和用水是否有影響,同時注意新埋線和換線的價格是不一樣的。

1. Hydropower positioning


The first step of hydropower reconstruction construction is hydropower positioning, which is to locate the position of the whole house switch socket and the location of the waterway interface according to the owner's requirements. The plumber needs to investigate the position of the switch, socket and faucet according to the direction on the drawing. clear. Moreover, we must pay attention to the principle of “water going to the sky and electricity to go to the ground”, that is, the water pipes go to the ceiling, the strong and weak electricity should go as far as possible, and the strong and weak electricity cannot cross, and the parallel distance needs to be more than 30 cm.


The location of the distribution box needs to be designed with ease of use, concealment and safety in mind. Also pay attention to the direct connection with the external main line, the electrical circuit can not be concealed in the load-bearing wall, inside the column.


The sockets, switches and luminaire lines in the circuit are designed to take into account the variability of the indoor space, to prepare for the use of different spaces, and to reduce the obstacles for re-planning design of some users during use, such as desks and decorative cabinets. Whether the movement of electrical equipment has an impact on the circuit and water, and at the same time pay attention to the price of the new buried line and the line change is not the same.

中航城

2、打槽


水電定位好以后,就需要打槽。好的打槽師傅打出的槽基本是一條直線,而且深度也很有保證,而且槽邊基本沒有什么毛齒。注意打槽之前,務必讓水電工將所有的水電走向在墻上畫出來表面,并對照水電圖,看是否一致。

2, slotting


After the hydropower is positioned, it needs to be grooved. The slot made by a good slotting master is basically a straight line, and the depth is also very guaranteed, and the slot edge has basically no teeth. Be sure to let the plumber go all the way to the surface of the wall before the slotting, and check the water and electricity to see if it is consistent.

中航城

3、埋線


水電改造中的埋線非常重要,首先是電線的穿管,電線穿管時強弱電不能在同一管內,而且相差的具體需在30厘米左右,電線在管內不能有接頭,接頭一般是重新接一個轉接口,以保證電路的正常運行,電線一定要穿管才能預埋,不能直接將電線埋在槽內。水路走上水時應該注意冷熱水的位置,避免接錯的情況發生。

3, embedding


The embedding line in the hydropower transformation is very important. The first is the thread of the wire. When the wire is worn, the strong and weak electricity cannot be in the same pipe, and the specific difference is about 30 cm. The wire cannot have a joint in the pipe. The joint is usually reconnected. A transfer interface to ensure the normal operation of the circuit, the wire must be piped to be embedded, and the wire cannot be buried directly in the slot. When the waterway is on the water, you should pay attention to the location of the hot and cold water to avoid the wrong situation.

中航城

以上便是小編介紹的水電改造施工的相關知識,水電改造一直是家裝中非常重要的環節,大家在做水電改造時一定要多加注意,避免施工人員出現偷工減料的情況,以保證水電改造良好的施工質量。

The above is the related knowledge of hydropower reconstruction construction introduced by Xiaobian. Hydropower transformation has always been a very important part of home improvement. Everyone must pay more attention when doing hydropower transformation, to avoid the situation of construction workers cutting corners to ensure that hydropower transformation is good. Construction Quality.


97%的人都看過:

>>>別墅房屋怎么改造?老別墅改造的3個注意事項
>>>70平米二手房改造費用要多少錢?二手房改造費用清單
>>>昆明二手房改造費用要多少?二手房改造怎么省錢?
>>>90平米二手房改造裝修費用要多少?二手房改造費用清單
>>>100平米二手房改造翻新要多少錢?二手房改造費用明細表


上一條:老別墅電路改造如何驗收?4個別 下一條: 昆明老別墅水電改造誤區有哪些?

免費報價 裝修預約

16年專注居家生活品質
30000+別墅大宅設計施工作品
90%+的客戶把紫蘋果推薦給自己親友

紫蘋果官網:zpg.com.cn

咨詢電話:400-600-2521

掃一掃手機瀏覽

掃一掃關注我們

紫蘋果聲明:

“紫蘋果”是經過商標局注冊認證,屬于紫蘋果裝飾集團獨有品牌。紫蘋果裝飾目前只在上海、蘇州、無錫、寧波、合肥、成都、南寧、貴陽、昆明、曲靖、大理、重慶等城市開設分公司; 其余地區相似紫蘋果公司不屬于紫蘋果裝飾集團。咨詢熱線:400-600-2521

Copyright ? 2017 zpg.com.cn All Rights Reserved. 滇ICP備10002477號-2 昆明紫蘋果裝飾工程有限公司版權所有

紫蘋果國際設計-匠心鑄就精品

×

提交成功
感謝您關注紫蘋果,我們將會在一個工作日內與您聯系!
我知道了
六合彩历史记录